CEA Myanmar Complete Installation of Massive Brewery Tanks

CEA Myanmar Complete Installation of Massive Brewery Tanks
Danny Gill

CEA Project Logistics Myanmar has completed the transportation and installation of two huge 18 Tonne vertical storage tanks at a Yangon brewery. The project was complex due to two cranes being required to operate and maneuver these tanks in a very narrow location outside the facility.

Before the tanks arrived, CEA teams had to prepare the installation area by affixing anchor bolts to each concrete tank base. When the first tank arrived both the 100 Tonne mobile crane and 30 Tonne tailing crane had to position themselves on both sides of the trailer in the narrow alley, which required slings to be attached to both ends of the tank as the cranes began the lift.

CEA-project-Logistics-Myanmar-Brewery-Tank-installation-7
Due to working in such a confined space each tank had to be lifted above and clear of the adjacent buildings, the crane then turned and lowered each tank onto its concrete base allowing for final alignment and the anchor bolts to be fixed. CEA Project Logistics Myanmar are quickly becoming transportation and installation specialists throughout the developing country, with an increasingly impressive portfolio of completed projects.

Project Cargo
Danny Gill

Danny is currently a Contributing Writer for Airfreight Logistics and Logistics Manager (LM) and is quite the foodie. He’s always on the hunt for new and exciting dishes to sample, and is never one to back down from a spicy challenge. His travels have taken him around the world, and he’s been able to experience many different cultures (and food).

More in Project Cargo

AAL Delivers 13 Giant Haul Trucks For Siberian Mining Project

Danny GillJuly 13, 2017

AAL Completes 9-Month Assignment for Egypt’s Multi-Billion-Dollar Megaproject

Danny GillJune 8, 2017

CEA Thailand Complete Demobilization Project

Danny GillMay 13, 2017
hansa

Hansa Heavy Lift Transports Range of Subsea Equipment to Indonesia

Danny GillApril 20, 2017

CEA Relocates Head Office & Songkhla Base

Danny GillMarch 30, 2017
CEA transports Helicopter

CEA Completes Specialized Helicopter Transport Project

Danny GillFebruary 6, 2017
siemens

Siemens to Supply Turnkey Power Plant to Thailand

Danny GillJanuary 30, 2017

CEA Carries Out Large Breakbulk & OOG Project

Danny GillJanuary 19, 2017
Epic Transports project cargo transports

Watch 7 of the Most Epic Transports in History

Vip KlangchaneeJanuary 10, 2017